PRE-ENGINEERING STUDY – VIGGIANO, ITALY
GOALS
- Replacement of Emergency Shutdown Systems due to obsolescence of the product;
- upgrading of the supervision system and substitution of the Opertator Workstations and Servers with Virtualized machines;
- Expansion of the existing ESD system for the management and acquisition of new signals to be commissioned during the plant shutdown scheduled in 2021.
Sector: Oil&Gas
Year: 2019
Location: Centro Oli Val D’Agri – Viggiano (PZ)
Direct client: Key Solution
Final client: ENI
MAIN ACTIVITIES
- Evaluation of technical aspects and operation constraints;
- Evaluation of the Preliminary Study issued by System Vendor (ABB);
- Cause & Effect analysis to identify Critical loops;
- Issue and discussion of the safety systems test procedure;
- Meetings with the System Vendor to evaluate all the technical aspects and critical issues related to the replacements of the systems and to define the activities to be sceduled;
- Meetings with the client and vendor for the definition of the schedule during plant shutdown in 2021 and in the previous months.
SOLUTIONS
- ABB ICSS (safeguard and 800xA) with more than 50000 I/Os;
- Analysis of existing System Architecture;
- Analysis for ESD logic upgrading for SIL certification;
- Study to maintain Line monitoring of Digital Output Signals (DO);
- Segregation of DCS and DCS control networks.